Friday 26 November 2010

Skelmersdale - Day 3

The counters are now all out and the flooring is down ready for the install of the new help desk and self service.
Strictly come dancing 2011?


The new Help Desk
25th Nov
The day got off to a frustrating start with me waiting 3 hours for a courier to pick up the self service hardware to be on site for a 13:00 install (The courier eventually turned up at 15:20).  The old addage 'if you want something doing do it yourself' came in to play!  I arrived on site with a fully laden car at 12:55 and installation, of the self service, commenced.
The new help desk was already installed although joiners were called in to remove the tops later on so that the electricians and data cablers could get at the cable trunking with ease.
The self service install could not be completed because of network access issues for the 3M engineer.  The 26th will prove to be a challenging day!

AV is getting a new home at Skelmersdale