Tuesday 23 November 2010

Day 1 - Skelmersdale

Carpet removed ready for laminate

Main counter to be removed


Counter now removed



Day one saw the removal of the main counter and the floor screed applied ready for the laying of the laminate floor.  The self service furniture was delivered to site with installation scheduled for Thursday afternoon. 
A problem, regarding the core holes for the data and electrics, was encountered where the drills were unable to cut through the steel reinforced mesh.  The core holes were reduced in size to overcome this problem and holes were drilled for the new help desk, Pods and Self Service prior to the screed going down.
The security barrier was also removed

No comments:

Post a Comment