Monday 22 November 2010

Phase 2 Installations - The week ahead 22nd - 28th November

Work will be carried out at 2 libraries this week, Accrington and Skelmersdale.

Skelmersdale:
  1. Closes 23rd - 26th November inclusive.
  2. Counter removed Tuesday 23rd
  3. Self Service furniture delivered Tuesday 23rd
  4. Commence screeding floor 23rd
  5. Commence laying flooring 24th
  6. Finish flooring 25th
  7. Install new help desk Thursday 25th in the afternoon
  8. Install self service Thursday pm / Friday am
  9. Complete electrics to new help desk Friday 26th
  10. Configure and test Self Service Friday 26th.
  11. Refresher training Friday pm (if needed)
  12. 'Live' Saturday 27th November
Accrington:
  1. Wednesday 24th - Remove electrics/data from enquiry desk
  2. Remove sections from the enquiry desk to remove from site wednesday 24th.
  3. Deliver and Install 2 in No. Staff Pods.
  4. Data for staff pods to be installed.
  5. Temporary power to be set up for staff pods.  

No comments:

Post a Comment