Tuesday, 7 December 2010

Leyland Library - Day 2

The self service hardware is being installed today and the flooring is being laid.  The leaflet wall has been moved but the joiner will need to fix the units to the partition screens.
Self service on back wall and flooring ready for screed
It is the intention to screed the floor and then lay the laminate on the same day.


No comments:

Post a Comment