What a hectic day, all trades onsite on a converging path!
A lesson learnt today was to ensure that the help desk tops are left off until the power, data and telephony is installed. This sped up the process.
All pods and integrated shelving has turned up and been installed now library staff can get to work installing the PCs on the pods and the new helpdesk. There were a few issues remaining but all in all the library looks fantastic.
Self Service up and running |
Nearly there! |
The new AV area |
We're up and running and it's only 16:50 on a Friday! |