Wednesday, 24 November 2010

Accrington Library 24th November

Enquiry desk is being shortened today.

Before



After


The data for the staff pods is now in place as are the staff Pods.  The sections of the enquiry desk have now been removed with the adapted section to return with the additional DVD pod and integrated shelving next week.

Tuesday, 23 November 2010

Day 1 - Skelmersdale

Carpet removed ready for laminate

Main counter to be removed


Counter now removed



Day one saw the removal of the main counter and the floor screed applied ready for the laying of the laminate floor.  The self service furniture was delivered to site with installation scheduled for Thursday afternoon. 
A problem, regarding the core holes for the data and electrics, was encountered where the drills were unable to cut through the steel reinforced mesh.  The core holes were reduced in size to overcome this problem and holes were drilled for the new help desk, Pods and Self Service prior to the screed going down.
The security barrier was also removed

Monday, 22 November 2010

Skelmersdale Enquiry desk removed

The enquiry desk at Skelmersdale library has been removed and is now waiting for the closure before laying the laminate floor.
Published with Blogger-droid v1.6.5

October usage statistics

The usage figures by Issue/Discharge/Renewal through Self Service by site:


(CPP) Preston (Harris) 38.39%

(EBU) Burnley 52.98%

(ECO) Colne 58.75%

(ENE) Nelson 74.22%

(HHA) Haslingden 52.27%

(NLA) Lancaster 59.26%

(NMO) Morecambe 34.57%

(NPO) Poulton 41.16%

(SCH) Chorley 48.55%

(SOR) Ormskirk 47.88%

Phase 2 Installations - The week ahead 22nd - 28th November

Work will be carried out at 2 libraries this week, Accrington and Skelmersdale.

Skelmersdale:
  1. Closes 23rd - 26th November inclusive.
  2. Counter removed Tuesday 23rd
  3. Self Service furniture delivered Tuesday 23rd
  4. Commence screeding floor 23rd
  5. Commence laying flooring 24th
  6. Finish flooring 25th
  7. Install new help desk Thursday 25th in the afternoon
  8. Install self service Thursday pm / Friday am
  9. Complete electrics to new help desk Friday 26th
  10. Configure and test Self Service Friday 26th.
  11. Refresher training Friday pm (if needed)
  12. 'Live' Saturday 27th November
Accrington:
  1. Wednesday 24th - Remove electrics/data from enquiry desk
  2. Remove sections from the enquiry desk to remove from site wednesday 24th.
  3. Deliver and Install 2 in No. Staff Pods.
  4. Data for staff pods to be installed.
  5. Temporary power to be set up for staff pods.